Lesson Simple arithmetic word problems on "rate of work"

Algebra ->  Numeric Fractions Calculators, Lesson and Practice -> Lesson Simple arithmetic word problems on "rate of work"      Log On


   


This Lesson (Simple arithmetic word problems on "rate of work") was created by by ikleyn(52814) About Me : View Source, Show
About ikleyn:

Simple arithmetic word problems on "rate of work"


Problem 1

A farmer ploughs his land in  12  days if he uses  5  tractors.
How long will it take if he uses only  3  tractors?

Solution

The entire job is 12*5 = 60 tractor-days.


With using only 3 tractors, it will take  60%2F3 = 20 days  to complete the job.    ANSWER

Problem 2

25  men start a job which they can finish in  40  days.  After  16  days  10  men leave.
How many days in total did it take for the entire job to be finished?

Solution

The entire job is 25*40 = 1000 man-days.


After 16 days 25 men completed 16*25 = 400 man-days, and  1000-400 = 600 man-days left to complete.


The answer to the problem's question is  600%2F%2825-10%29 = 600%2F15 = 40 days.   ANSWER

Problem 3

A certain job can be done by  72  men in  100  days.  There were  80  men at the start of the project
but after  40  days,  30  of them had to be transferred to another project.
How long will it take the remaining workforce to complete the job?

Solution

Since the job can be done by 72 men in 100 days, it means that the entire job is 72*100 = 7200 man-days.


80 men in 40 days completed a part of the job, which is 3200 man-days; the remaining job is 7200-3200 = 4000 man-days.


The remaining workforce is 80-30 = 50 men.


They will complete the remaining part of the gob in  4000/50 = 80 days.    ANSWER

Problem 4

Eight man take  12  days to cultivate a piece of land.
After working for  3  days,  10  more man were employed.
How long will it take to  18 man  to cultivate the rest of the land ?

Solution

I will present two solutions.

              Solution 1


The entire job is 8*12 man-days.


In 3 days,  the part of the job of  3*8 = 24  man-days is complete;
the rest of the job, which is  96-24 = 72 man-days, remains.

Now 8+10 = 18 man work on the remaining part of the job.
They will complete the job in 72/18 = 4 days.


ANSWER.  18 man will complete the remaining part of the job in 4 days.



              Solution 2


After 3 days, 1/4 of the job was done; 3/4 of the job remained.


8 workers would complete the remaining job in 9 days (under regular conditions).


But 8+10 = 18 workers will complete the remaining job in  


    9%2A%288%2F18%29 = 8%2F2 = 4  days.    


You get the same answer.

Problem 5

If  18  pumps can raise  2170  tons of water in  10  days,  working  7  hours a day,
in how many days will  16  pumps raise  1736  tons of water,  working  9  hours a day?

Solution

Raising 2170 tons of water requires  18*10*7 = 1260 pump-hours.


So, the rate is  2170%2F1260 = 31%2F18  tons of water per one pump-hour.


To raise 1736 tons of water, using 16 pumps working 9 hours a day,

    1736%2F%28%2831%2F18%29%2A16%2A9%29 = %281736%2A18%29%2F%2831%2A16%2A9%29 = 7 days is needed.

Problem 6

Five workers have been hired to complete a job.
If one additional worker is hired, they could complete the job  6  days earlier.
If the job needs to be completed  32  days earlier,  how many additional workers should be hired?

Solution

                    Solve it step by step.

      Step 1 - determine the number of days needed for 5 workers
               to complete the job.


Let d be the number of days for 5 workers to complete the job.

Then the entire job is 5d worker-days.


6 workers could complete the job in (d-6) days.

Hence, from this perspective, the entire work is  6*(d-6)  worker-days.


It gives us this equation

    5d = 6(d-6),

from which we get

     5d = 6d - 36  --->  36 = 6d - 5d  --->  36 = d.


Hence, 5 workers need 36 days to complete the job,  and the entire job is 5*36 = 180 worker-days.



      Step 2 - determine the number of workers needed 
               to complete the job in 32 days earlier.


The question wants the job be complete in 36-32 = 4 days.


It requires 180/4 = 45 workers.



      Step 3 - determine the number of additional workers 
               to be hired.


The number of additional workers is  45 - 5 = 40.


ANSWER.  40 additional workers should be hired to complete the job in 32 days earlier.


My other lessons on arithmetic word problems in this site are
    Arithmetic word problems to solve them MENTALLY
    Solving arithmetic word problems by reasoning
    Simple arithmetic word problems solved in a right way
    Arithmetic coin problems
    Simple and simplest arithmetic Travel & Distance problems
    Typical arithmetic Travel & Distance problems
    Entertaining catching up arithmetic Travel & Distance problems
    Other basic arithmetic Travel & Distance problems
    Advanced arithmetic word problems on Travel & Distance
    Finding travel time and average rate
    Flying back and forth

    OVERVIEW of the first group of lessons on arithmetic word problems

To see the whole list of lessons on arithmetic problems,  use this link  Arithmetic problems - YOUR ONLINE TEXTBOOK
It is your way to the entry page of the online textbook on Arithmetic problems.



This lesson has been accessed 776 times.