SOLUTION: Six workers worked 14 days and complete 80%of the work. How many days did it take to do the whole job?

Algebra ->  Numeric Fractions Calculators, Lesson and Practice -> SOLUTION: Six workers worked 14 days and complete 80%of the work. How many days did it take to do the whole job?      Log On


   



Question 315351: Six workers worked 14 days and complete 80%of the work. How many days did it take to do the whole job?
Answer by rfer(16322) About Me  (Show Source):
You can put this solution on YOUR website!
14/.8=17.5 days