Question 951558: A contructor undertakes to build a wall 1000 meter long in 50 days. He employed 56 men but at the end of 27 days he finds that only 448 meter of wall is build. How many extra men must the contractor employ so that the wall is completed in time .
Found 3 solutions by stanbon, ankor@dixie-net.com, MathTherapy:
Answer by stanbon(75887) About Me  (Show Source):
You can put this solution on YOUR website!
A contructor undertakes to build a wall 1000 meter long in 50 days. He employed 56 men but at the end of 27 days he finds that only 448 meter of wall is build. How many extra men must the contractor employ so that the wall is completed in time .
----
# of men is directly related to length of wall and
indirectly related to # of days.
----
m = k*L/D
-----------
Solve for "k" using "He employed 56 men but at the end of 27 days he finds that only 448 meter of wall is build"
56 = k*448/27
k = (27*56)/448
k = 3.375
------
Equation:
m = 3.375L/D
How many extra men must the contractor employ so that the wall is completed in time .
m = 3.375(1000-448)/(50-27)
m = 3.375*552/23
m = 81 (# of men he'll need to finish the job on time)
------------
Cheers,
Stan H.
---------------

Answer by ankor@dixie-net.com(22740) About Me  (Show Source):
You can put this solution on YOUR website!
A constructor undertakes to build a wall 1000 meter long in 50 days.
He employed 56 men but at the end of 27 days he finds that only 448 meter of wall is build.
Find how many man-days required per meter
%28%2856%2A27%29%29%2F448 = 3.375 man-days per meter
:
How many extra men must the contractor employ so that the wall is completed in time.
He has 1000 - 448 = 552 meters to build
That will require 552*3.375 = 1863 man-days
let m = number of additional men, he has 50 - 27 = 23 days to complete the wall
23(m + 56) = 1863
23m + 1288 = 1863
23m = 1863 - 1288
23m = 575
m = 575/23
m = 25 additional men required


Answer by MathTherapy(10552) About Me  (Show Source):
You can put this solution on YOUR website!
A contructor undertakes to build a wall 1000 meter long in 50 days. He employed 56 men but at the end of 27 days he finds that only 448 meter of wall is build. How many extra men must the contractor employ so that the wall is completed in time
highlight_green%2825%29 extra men are needed to complete remaining 552 m in 23 days.