Question 1199446
:
If 20 men can lay 36 m of pipe in 8 hours. How long would 25 men take to lay the next 54 m of pipe
Answer by
josgarithmetic(39617)
(
Show Source
):
You can
put this solution on YOUR website!
N, how many workers
R, work rate for 1 worker
T, time of working
W, amount of work
----basic rule
let r be the work rate of any one man, and x be the time asked for.
If you divide the second equation by the first equation,..........