SOLUTION: 2 men and 7 boys complete a work in 14 days .3 men and 8 boys complete it in 11 days.then in how many days will 8 men and 6 boys complete the work ?

Algebra ->  Finance -> SOLUTION: 2 men and 7 boys complete a work in 14 days .3 men and 8 boys complete it in 11 days.then in how many days will 8 men and 6 boys complete the work ?       Log On


   



Question 1094224: 2 men and 7 boys complete a work in 14 days .3 men and 8 boys complete it in 11 days.then in how many days will 8 men and 6 boys complete the work ?

Answer by ikleyn(52787) About Me  (Show Source):
You can put this solution on YOUR website!
.
Let M be the rate of work for a man and B be the rate of work for a boy.
Then from the condition you have this system of equations

2M + 7B = 1%2F14,     (eq1)
3M + 8B = 1%2F11.     (eq2)


Solve the system (it is just a technique) and find M and B.


Then evaluate 8M + 6B and calculate reciprocal.

For similar problems, see the lesson
    - Solving rate of work problem by reducing to a system of linear equations
in this site.