SOLUTION: A small factory planned to produce a batch of men’s shirts in 8 days. But producing 10 more shirts per day than planned, they finished the task one day early. How many shirts per d

Algebra ->  Finance -> SOLUTION: A small factory planned to produce a batch of men’s shirts in 8 days. But producing 10 more shirts per day than planned, they finished the task one day early. How many shirts per d      Log On


   



Question 1065526: A small factory planned to produce a batch of men’s shirts in 8 days. But producing 10 more shirts per day than planned, they finished the task one day early. How many shirts per day was the factory planning to produce?

Found 2 solutions by Fombitz, ikleyn:
Answer by Fombitz(32388) About Me  (Show Source):
You can put this solution on YOUR website!
Rate x Time = Output
At first,
R%5B1%5D%2A8=N
However with the rate increase,
%28R%5B1%5D%2B1%29%2A7=N
They both equal N so set them equal to each other,
R%5B1%5D%2A8=%28R%5B1%5D%2B1%297
8R%5B1%5D=7R%5B1%5D%2B7
R%5B1%5D=7
So then,
N=7%2A8
N=56

Answer by ikleyn(52781) About Me  (Show Source):
You can put this solution on YOUR website!
.
A small factory planned to produce a batch of men’s shirts in 8 days. But producing 10 more shirts per day than planned,
they finished the task one day early. How many shirts per day was the factory planning to produce?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Rate x Time = Output
At first,
R%5B1%5D%2A8=N
However with the rate increase,
%28R%5B1%5D%2B10%29%2A7=N
They both equal N so set them equal to each other,
R%5B1%5D%2A8=%28R%5B1%5D%2B10%297
8R%5B1%5D=7R%5B1%5D%2B70
R%5B1%5D=70
So then,
N=70%2A8
N=560

Answer. How many shirts per day was the factory planning to produce? 70.