SOLUTION: How would I calculate what the pieces per hour are if I had 2097 pieces produced with 9 people working for 2 hours (120 min)
Algebra ->
Average
-> SOLUTION: How would I calculate what the pieces per hour are if I had 2097 pieces produced with 9 people working for 2 hours (120 min)
Log On
You can put this solution on YOUR website! How would I calculate what the pieces per hour are if I had 2097 pieces produced with 9 people working for 2 hours (120 min)
:
If you want pieces per hr per man, you can use man-hrs
9 * 2 = 18 man-hrs to produce 2097 pieces
: ~ 117 per hr per man