SOLUTION: 15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the

Algebra ->  Customizable Word Problem Solvers  -> Evaluation -> SOLUTION: 15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the      Log On

Ad: Over 600 Algebra Word Problems at edhelper.com


   



Question 446845: 15 Java programmers, working in a constant pace, finish a web page in 3 days. If
after one day, 9 programmers quit, how many more days are needed to finish the
remainder of the job?

Answer by mohammadrezai(14) About Me  (Show Source):
You can put this solution on YOUR website!
Whole the work needs 45 man/day work.
And after 1 day, 15 man/day done and 30 man/day work remained.
There for 6 programmers must 5 day work that the work completed.