Question 927434: A manufacturer contemplating the purchase of new tool making equipment has specified that on the average the equipment should not require more than 10 minutes of set up time per hour of operation. The purchasing agent visits a company where the equipment being considered is installed; from records there he notes that 40 randomly selected hours of operation included a total of 7 hours and 30 minutes of set up time, and the standard deviation of set up time per hour was 3 minutes. Based on this sample result, can the assumption that the equipment meets the set up time specification be rejected at the 1 percent level of significance?
Answer by ewatrrr(24785)   (Show Source): You can put this solution on YOUR website!
set up time specification: t ≤ 10min
Sample: mean = 450min/40 = 11.25min, sd = 3min

z(11.25) = 1.25/(3/sqrt(40) = 2.6352
P(z > 2.6352) = .0042
........
1 percent level of significance
.0042< .01, equipment does NOT meet the set up time specification

RELATED QUESTIONS

A school has just purchased new computer equipment for The graph shows the depreciation... (answered by ewatrrr,ikleyn)
According to a school’s budget, the money spent on buying new equipment and money spent (answered by greenestamps)
Assume that a manufacturer can purchase a needed component from a supplier at a cost of (answered by ikleyn)
Megan's Bakery recently spent a total of $559 on new equipment, and their average hourly... (answered by greenestamps)
Mark's Bakery recently spent a total of $830 on new equipment, and their average hourly... (answered by josmiceli)
Dominique is purchasing a car priced at $20,000. At the time of purchase, he will also... (answered by math_tutor2020)
A manufacturer of exercise equipment uses a markup rate of 30%. One of the manufacturer's (answered by Alan3354)
There are 60% heating equipment 25% electrical equipment and 15% plumbing equipment in a... (answered by stanbon)
a piece of equipment(S) annd another piece(G) is both used for 6 hours for $90. equipment (answered by Theo)