Question 506533: One man can paint a garage in 28 hours. After working for 12 hours, he was given a new job, and a second man finished painting in 18 hours. How long would the second man take take to paint to whole garage? Answer by nerdybill(7384) (Show Source):
You can put this solution on YOUR website! One man can paint a garage in 28 hours. After working for 12 hours, he was given a new job, and a second man finished painting in 18 hours. How long would the second man take take to paint to whole garage?
.
Let x = time (hours) it takes second man to paint whole garage
then
12(1/28) + 18(1/x) = 1
multiplying both sides by 28x:
12(x) + 18(28) = 28x
12x + 504 = 28x
504 = 16x
31.5 hours = x