SOLUTION: there are 5 men working for 24 hours for 5 days to complete a brick wall. how many days can one man complete the same job if he only works for 8 hours a day? my answer was 75 bu

Algebra ->  Rate-of-work-word-problems -> SOLUTION: there are 5 men working for 24 hours for 5 days to complete a brick wall. how many days can one man complete the same job if he only works for 8 hours a day? my answer was 75 bu      Log On


   



Question 316430: there are 5 men working for 24 hours for 5 days to complete a brick wall. how many days can one man complete the same job if he only works for 8 hours a day?
my answer was 75 but i was told that it was wrong. can you help? thanks!

Found 2 solutions by Alan3354, scott8148:
Answer by Alan3354(69443) About Me  (Show Source):
You can put this solution on YOUR website!
there are 5 men working for 24 hours for 5 days to complete a brick wall. how many days can one man complete the same job if he only works for 8 hours a day?
------------------
Do the 5 men work 24 hours each day for 5 days?

Answer by scott8148(6628) About Me  (Show Source):
You can put this solution on YOUR website!
one man will take five times as many days as five men, so twenty-five 24 hour days

if the one man only works 8 hrs per day, then it takes seventy-five 8 hr days

I don't see what's wrong with your answer


another approach ___ (5 men)(24 hr / day)(5 days) = 600 man-hrs

(600 man-hrs) / (1 man) / (8 hrs / day) = 75 days