document.write( "Question 128983: A worker can finish a job in 18 days.An other worker can do the same work but in 24 days and an other worker can do the same work in 30 days . If the 3 workers work 6 days together,what part of the job will be done ??
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #94321 by ptaylor(2198)\"\" \"About 
You can put this solution on YOUR website!

\n" ); document.write( "Let x=part of job that will be done with all three working together for 6 days
\n" ); document.write( "Worker #1 works at the rate of 1/18 of the job per day or 6/18 of the job in 6 days
\n" ); document.write( "Worker #2 works at the rate of 1/24 of the job per day or 6/24 of the job in 6 days
\n" ); document.write( "Worker #3 works at the rate of 1/30 of the job per day or 6/30 of the job in 6 days\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "So together they do:
\n" ); document.write( "6/18+6/24+6/30 of the job in 6 days and this equals:\r
\n" ); document.write( "\n" ); document.write( "1/3+1/4+1/5 =20/60+15/60+12/60 =x=
\n" ); document.write( "47/60 of the job in 6 days\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Hope this helps---ptaylor
\n" ); document.write( "
\n" );