document.write( "Question 126538: If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days? \n" ); document.write( "
Algebra.Com's Answer #92697 by josmiceli(19441)\"\" \"About 
You can put this solution on YOUR website!
If 6 men can do the job in 14 days, it will take 1 man 6 times as long
\n" ); document.write( "so. 1 man will take \"6%2A14+=+84\" days
\n" ); document.write( "\"x%2F21+=+1%2F84\"
\n" ); document.write( "You can read this as: what part of the job can be done by 1 man in 21 days
\n" ); document.write( "if 1 man can do 1 job in 84 days
\n" ); document.write( "\"x+=+1%2F4\"
\n" ); document.write( "So, 1 man can do 1/4 of the job in 21 days
\n" ); document.write( "And 4 men can do 4 times as much, or 1 job, done in the same amount tof time
\n" ); document.write( "It takes 4 men to do the job in 21 days\r