document.write( "Question 1027961: A takes 10 days less than the time taken by B to finish an embroidery work. If both A and B together can finish the work in 12 days. Find the time taken by B alone to finish the work. \n" ); document.write( "
Algebra.Com's Answer #853891 by josgarithmetic(39792)\"\" \"About 
You can put this solution on YOUR website!
Workrate for A, \"1%2F%28b-10%29\"\r
\n" ); document.write( "\n" ); document.write( "Workrate for B, \"1%2Fb\"\r
\n" ); document.write( "\n" ); document.write( "Rate of A and B together, \"1%2F12\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Meaning \"1%2F12=1%2F%28b-10%29%2B1%2Fb\". Solve for b.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "That should become \"b%5E2-34b%2B120=0\".
\n" ); document.write( "Two numbers will occur for b, but the realistic result is \"highlight%28b=30%29\".
\n" ); document.write( "
\n" );