document.write( "Question 1027961: A takes 10 days less than the time taken by B to finish an embroidery work. If both A and B together can finish the work in 12 days. Find the time taken by B alone to finish the work. \n" ); document.write( "
Algebra.Com's Answer #853891 by josgarithmetic(39792) ![]() You can put this solution on YOUR website! Workrate for A, \n" ); document.write( "\n" ); document.write( "Workrate for B, \n" ); document.write( "\n" ); document.write( "Rate of A and B together, \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Meaning \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "That should become \n" ); document.write( "Two numbers will occur for b, but the realistic result is |