document.write( "Question 1081944: 80 men can finish the job in 60 days. At the 16th day, 5 men were laid off and at the 45th day, 10 men were hired. How many days were they delayed finishing the job. \n" ); document.write( "
Algebra.Com's Answer #853795 by MathTherapy(10719) You can put this solution on YOUR website! \r\n" ); document.write( "80 men can finish the job in 60 days. At the 16th day, 5 men were laid off and at the 45th day, 10 men were hired.\r\n" ); document.write( "How many days were they delayed finishing the job.\r\n" ); document.write( "**************************************************\r\n" ); document.write( "7+-day delay, from the other person is WRONG!!\r\n" ); document.write( "\r\n" ); document.write( "80-MAN rate:\n" ); document.write( " |