document.write( "Question 773494: A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to another job. how many more days will the remaining men finish the job? \n" ); document.write( "
Algebra.Com's Answer #853780 by josgarithmetic(39736) ![]() You can put this solution on YOUR website! r, the work rate of 1 man\r \n" ); document.write( "\n" ); document.write( "For 5 men working 10 days to do 1 \"piece of work\" \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "or\r \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Five men worked for 4 days and then 2 men worked for some x days to finish. \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( "\n" ); document.write( " |