document.write( "Question 1205910: It takes 3 people 4 days to build a garage.
\n" ); document.write( "A) How long does it take one person to build the garage?
\n" ); document.write( "B)How long does it take four people to build the garage?
\n" ); document.write( "C)How many people are needed to build the garage in 2 days?
\n" ); document.write( "

Algebra.Com's Answer #843002 by greenestamps(13200)\"\" \"About 
You can put this solution on YOUR website!


\n" ); document.write( "The other tutor shows one common method for answering the questions by finding the total number of man-days it takes to build the garage.

\n" ); document.write( "A different way for solving problems like this is to look at how each change in the numbers affects the other numbers.

\n" ); document.write( "We are given that it takes 3 people 4 days to build the garage. Using that information....

\n" ); document.write( "A) How long does it take one person to build the garage?
\n" ); document.write( "1/3 as many workers means 3 times as many days. ANSWER: 4*3 = 12

\n" ); document.write( "B) How long does it take four people to build the garage?
\n" ); document.write( "4/3 as many workers means 3/4 as many days. ANSWER: (3/4)*4 = 3

\n" ); document.write( "C) How many people are needed to build the garage in 2 days?
\n" ); document.write( "Half as many days means twice as many workers. ANSWER: 3*2 = 6

\n" ); document.write( "
\n" ); document.write( "
\n" );