document.write( "Question 1203763: It takes 20 men 60 days to complete a building work.how many days longer would it take 15 men, assuming that they all work at the same rate (formula method)
\n" ); document.write( "
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #839596 by greenestamps(13200)\"\" \"About 
You can put this solution on YOUR website!


\n" ); document.write( "I don't know exactly what method you are calling the \"formula method\".... But simple logical reasoning can find the answer with far less work than with any formal algebra.

\n" ); document.write( "15 men working instead of 20 is 15/20 = 3/4 as many men, so to complete the job requires 4/3 as many day.

\n" ); document.write( "4/3 of 60 days is 80 days, which is 20 days more than 60.

\n" ); document.write( "ANSWER: 20 more days