document.write( "Question 1191067: It takes 5 people 6 days to paint a house, working 8 hour shifts. \r
\n" ); document.write( "\n" ); document.write( "a) how long would it take 4 people to complete the same job? \r
\n" ); document.write( "\n" ); document.write( "b) how many people would be needed to complete the same job in less than 4 days?
\n" ); document.write( "

Algebra.Com's Answer #822816 by ikleyn(52799)\"\" \"About 
You can put this solution on YOUR website!
.
\n" ); document.write( "It takes 5 people 6 days to paint a house, working 8 hour shifts.
\n" ); document.write( "a) how long would it take 4 people to complete the same job?
\n" ); document.write( "b) how many people would be needed to complete the same job in less than 4 days?
\n" ); document.write( "~~~~~~~~~~~~~~~~\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "
\r\n" );
document.write( "The entire job is 5*6 = 30 working days.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "(a)  With 8 hours shift, 4 workers will complete the job in  \"30%2F4\" = 7 \"1%2F2\"  working days = 7.5 working days = 7 days and 4 hours.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "(b)  \"30%2F4\" = 7.5;  therefore,  at least 8 workers should be employed to complete the job in less than 4 days.\r\n" );