document.write( "Question 1185686: 4 skilled workers can complete a job in 5 days. 5 semi-skilled workers can complete the same job in 6 days. How long does it take 1 skilled work and 1 semi-skilled worker to complete the same job if they work together? \r
\n" ); document.write( "\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #816531 by ikleyn(52790)\"\" \"About 
You can put this solution on YOUR website!
.
\n" ); document.write( " 4 skilled workers can complete a job in 5 days. 5 semi-skilled workers can complete the same job in 6 days.
\n" ); document.write( "How long does it take 1 skilled work and 1 semi-skilled worker to complete the same job if they work together?
\n" ); document.write( "~~~~~~~~~~~~~~~~\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "
\r\n" );
document.write( "Rate of work of one skilled worker is  \"1%2F%284%2A5%29\" = \"1%2F20\"  of the job per day.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "Rate of work of one semi-skilled worker is  \"1%2F%285%2A6%29\" = \"1%2F30\"  of the job per day.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "When one skilled worker and one semi-skilled worker work together, their combined rate of work is\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "    \"1%2F20\" + \"1%2F30\" = \"3%2F60\" + \"2%2F60\" = \"5%2F60\"  = \"1%2F12\"  of the job per day.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "It means that one skilled worker and one semi-skilled worker will complete the job in 12 days working together.    ANSWER\r\n" );
document.write( "
\r
\n" ); document.write( "\n" ); document.write( "Solved.\r
\n" ); document.write( "
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "
\n" ); document.write( "
\n" );