document.write( "Question 1184255: Hi
\n" ); document.write( "6 men do a job in 8 days. After 3 days 2 of the men are taken off the job. Find the time it takes for the job to be completed from start to finish. \r
\n" ); document.write( "\n" ); document.write( "Thanks
\n" ); document.write( "

Algebra.Com's Answer #814801 by greenestamps(13203)\"\" \"About 
You can put this solution on YOUR website!


\n" ); document.write( "Here are two other ways -- among many different possible ways -- of solving the problem.

\n" ); document.write( "Look at different ways and find what \"works\" best for you....

\n" ); document.write( "(1) After the first 3 days, there is enough work for the 6 men for another 5 days.

\n" ); document.write( "When 2 men are taken off the job, there are 4 men left; the number of workers gets multiplied by a factor of 4/6=2/3.

\n" ); document.write( "That means the amount of time remaining to finish the job gets multiplied by a factor of 3/2. So the number of days needed to finish the job is 5(3/2)=7.5

\n" ); document.write( "And so the job from start to finish takes 3+7.5 = 10.5 days.

\n" ); document.write( "(2) The entire job takes 6*8 = 48 man-days to complete.

\n" ); document.write( "The 6 men working for the first 3 days work a total of 6*3=18 man-days; there are 48-18=30 man-days of work remaining.

\n" ); document.write( "The number of days it takes 4 men to do the remaining 30 man-days of work is 30/4=7.5.

\n" ); document.write( "The total time for the job from start to finish is 3+7.5 = 10.5 days.