document.write( "6 men do a job in 8 days. After 3 days 2 of the men are taken off the job. Find the time it takes for the job to be completed from start to finish. \r
\n" );
document.write( "\n" );
document.write( "Thanks \n" );
document.write( "
Algebra.Com's Answer #814798 by math_helper(2461)![]() ![]() You can put this solution on YOUR website! \n" ); document.write( " |