document.write( "Question 1171750: A contractor undertook to build a building in 52 days and employed 24 men to work. Only 1/4 of the work was completed after 16 days. How many more men should be employed so that the work is completed
\n" ); document.write( "within the fixed time?
\n" ); document.write( "

Algebra.Com's Answer #796680 by josgarithmetic(39617)\"\" \"About 
You can put this solution on YOUR website!
r, rate of work 1 man
\n" ); document.write( "n, number of MORE men to help finish work\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"system%28%2824r%29%2816%29=1%2F4%2C%28n%2B24%29%28r%29%2852-16%29=3%2F4%29\"\r
\n" ); document.write( "\n" ); document.write( ".\r
\n" ); document.write( "\n" ); document.write( ".
\n" ); document.write( "A proportion can easily be made from those, simplified, and n solved-for.