document.write( "Question 445916: If A's rate of doing work is to B's is 6:8 and A does a piece of work in 50 days, how long will it take B to do it?\r
\n" ); document.write( "\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #795486 by wilmarugsad(1)\"\" \"About 
You can put this solution on YOUR website!
(A/B) =6:8
\n" ); document.write( "rate of A=1/50
\n" ); document.write( "rate of B=1/b
\n" ); document.write( "(6/8)=(1/50)/(1/b)
\n" ); document.write( "b=37.5 days