document.write( "Question 1165522: It takes 3 people to clean a pool in 4 hours. How many people do we need to clean 6 pools in 8 hours? \r
\n" );
document.write( "\n" );
document.write( "It seems to be a triple proportion but how exactly would I set it up?
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #790030 by ikleyn(52781)![]() ![]() You can put this solution on YOUR website! . \n" ); document.write( " \r\n" ); document.write( "\r\n" ); document.write( "One job (to clean 1 pool) is 3*4 = 12 man-hours.\r\n" ); document.write( "\r\n" ); document.write( "\r\n" ); document.write( "6 pools is 6 jobs, and they require 6*12 = 72 man-hours.\r\n" ); document.write( "\r\n" ); document.write( "\r\n" ); document.write( "The required number of people is\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |