document.write( "Question 1162589: Two companies working together can clear a parcel of land in 9 hours. Working alone, it would take Company A 8 hours longer to clear the land than it would Company B. How long would it take Company B to clear the parcel of land alone? (Round your answer to the nearest tenth.)\r
\n" ); document.write( "\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #786425 by josgarithmetic(39617)\"\" \"About 
You can put this solution on YOUR website!
Time for company B to do the job alone, b.
\n" ); document.write( "Time for company A to do the one job alone, b+8.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"1%2F%28b%2B8%29%2B1%2Fb=1%2F9\"\r