document.write( "Question 1162589: Two companies working together can clear a parcel of land in 9 hours. Working alone, it would take Company A 8 hours longer to clear the land than it would Company B. How long would it take Company B to clear the parcel of land alone? (Round your answer to the nearest tenth.)\r
\n" );
document.write( "\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #786425 by josgarithmetic(39617)![]() ![]() ![]() You can put this solution on YOUR website! Time for company B to do the job alone, b. \n" ); document.write( "Time for company A to do the one job alone, b+8.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( "\n" ); document.write( ".\r \n" ); document.write( "\n" ); document.write( ".\r \n" ); document.write( "\n" ); document.write( ". \n" ); document.write( " |