document.write( "Question 1161494: A cement factory estimates that 10 men must work for 8 hours each day to complete a job in 30 days. If only 8 men are to complete the job in 40 days, how long must they work each day? \n" ); document.write( "
Algebra.Com's Answer #785066 by josgarithmetic(39617)![]() ![]() ![]() You can put this solution on YOUR website! If r for the rate per hour of any 1 man, \n" ); document.write( "x number of hours each day for the question,\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Number of total work hours would be (workhours/day)*(numberofdays);\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "To solve for x, \n" ); document.write( " \n" ); document.write( ". \n" ); document.write( ". \n" ); document.write( " \n" ); document.write( "They work seven and a half hours each day. \n" ); document.write( " |