document.write( "Question 1157255: 6men can weed the farm for 16days.After working for 4 days 2 more men were added. For how long did they weed the farm? \n" ); document.write( "
Algebra.Com's Answer #780186 by greenestamps(13200)\"\" \"About 
You can put this solution on YOUR website!


\n" ); document.write( "The 6 men can to the job in 16 days; in the first 4 days, they can do 1/4 of the job. 3/4 of the job remains.

\n" ); document.write( "It would take the 6 men 12 more days to finish the job alone; but now 8 men are working.

\n" ); document.write( "Increasing the number of workers by a factor of 4/3 means the remaining job will take 3/4 as long. 3/4 of 12 days is 9 days.

\n" ); document.write( "ANSWER: The two added men worked for 9 days; the original 6 men worked for 4+9=13 days.

\n" ); document.write( "
\n" ); document.write( "
\n" );