document.write( "Question 1157207: A crew of 2 could put siding on a house in 30 hours. Another crew of 3 could do the same job in 24 hours. How long would it take all 5 people working together? \n" ); document.write( "
Algebra.Com's Answer #780048 by greenestamps(13200)![]() ![]() You can put this solution on YOUR website! \n" ); document.write( "Here is alternative to the standard algebraic solution method shown by the other tutor. \n" ); document.write( "Consider the least common multiple of the two given times: the LCM of 24 and 30 is 120. \n" ); document.write( "In 120 hours, the crew of 2 could put siding on 120/30 = 4 houses; the crew of 3 could put siding on 120/24 = 5 houses. So in 120 hours the two crews together could put siding on 4+5=9 houses. \n" ); document.write( "So the number of hours it would take the two crews together to put siding on 1 house is 120/9 = 40/3, or 13 1/3 hours, or 13 hours 20 minutes. \n" ); document.write( " \n" ); document.write( " |