document.write( "Question 1151742: Hi \r
\n" ); document.write( "\n" ); document.write( "If 2 teams work together they can finish a job in 8 days. The rate of work of the first team is 5/8 of the rate of the second team. How many days each team needs to complete this job working alone.\r
\n" ); document.write( "\n" ); document.write( "Thanks
\n" ); document.write( "

Algebra.Com's Answer #773599 by greenestamps(13198)\"\" \"About 
You can put this solution on YOUR website!


\n" ); document.write( "Since the rate of the first team is 5/8 the rate of the second team, when working together the first team does 5/13 of the work and the second team does 8/13 of the work.

\n" ); document.write( "So when the two teams working together do the job in 8 days, the first team does 5/13 of the work in those 8 days. So the number of days they would take to do the whole job alone is

\n" ); document.write( "\"8%2F%285%2F13%29+=+8%2A%2813%2F5%29+=+104%2F5+=+20.8\"

\n" ); document.write( "Similarly, since the second team does 8/13 of the work in those 8 days, the number of days they would take to do the job alone is

\n" ); document.write( "\"8%2F%288%2F13%29+=+8%2A%2813%2F8%29+=+13\"

\n" ); document.write( "ANSWERS:
\n" ); document.write( "The first team would take 20.8 days to do the job alone.
\n" ); document.write( "The second team would take 13 days to do the job alone.

\n" ); document.write( "
\n" ); document.write( "
\n" );