document.write( "Question 1143847: Hi\r
\n" );
document.write( "\n" );
document.write( "one team of workers completes a job in 10 days, while another team completes it in 8 days. The first team worked alone for 1 day. Then the second team joined and finished the job in N days. What is the value of N.\r
\n" );
document.write( "\n" );
document.write( "thanks \n" );
document.write( "
Algebra.Com's Answer #764765 by greenestamps(13200)![]() ![]() You can put this solution on YOUR website! \n" ); document.write( "Working together the whole time, the number of days it would have taken to do the job is \n" ); document.write( " \n" ); document.write( "But in the beginning only the first team worked for 1 day, completing 1/10 of the job. Since only 9/10 of the job remains, the number of days it takes the two team together to finish the job is \n" ); document.write( " \n" ); document.write( "ANSWER: N = 4 \n" ); document.write( " |