document.write( "Question 1142328: a) Describe the following terms as used in network analysis
\n" );
document.write( "i. Critical activity
\n" );
document.write( "ii. Super critical activity
\n" );
document.write( "iii. Float
\n" );
document.write( "iv. Sub-critical activity
\n" );
document.write( "b) R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times and sequences required.\r
\n" );
document.write( "\n" );
document.write( "Activity Preceding Activity Time in Days
\n" );
document.write( "Optimistic Most likely Pessimistic
\n" );
document.write( "Time Time Time
\n" );
document.write( "A
\n" );
document.write( "B
\n" );
document.write( "C
\n" );
document.write( "D
\n" );
document.write( "E
\n" );
document.write( "F
\n" );
document.write( "G
\n" );
document.write( "H
\n" );
document.write( "I
\n" );
document.write( "J
\n" );
document.write( "K -
\n" );
document.write( "-
\n" );
document.write( "-
\n" );
document.write( "A
\n" );
document.write( "B
\n" );
document.write( "C
\n" );
document.write( "D,E
\n" );
document.write( "B
\n" );
document.write( "H,F
\n" );
document.write( "G,I
\n" );
document.write( "J 6 6 24
\n" );
document.write( "6 12 18
\n" );
document.write( "12 12 30
\n" );
document.write( "6 6 6
\n" );
document.write( "12 30 48
\n" );
document.write( "12 30 42
\n" );
document.write( "18 30 54
\n" );
document.write( "17 29 47
\n" );
document.write( "14 28 48
\n" );
document.write( "14 28 48
\n" );
document.write( "6 6 24\r
\n" );
document.write( "\n" );
document.write( "Required:-
\n" );
document.write( "a) Draw a network to represent the above data
\n" );
document.write( "b) Determine the critical path of the project and the expected project length
\n" );
document.write( "c) Calculate the variance and standard deviation of the project
\n" );
document.write( "d) Compute the probability of completing the project within a period of 120 days
\n" );
document.write( "e) Suppose you want to shorten the completion time as much as possible and have the option of shortening any or all of B, C, D and G each by two days. Which would you shorten? What would be the new critical path?
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #763058 by Alan3354(69443)![]() ![]() You can put this solution on YOUR website! Nope. \n" ); document.write( " |