document.write( "Question 1134054: 36 people can construct a house in 15 days but the owner would like to finish the work in 10 days how many more workers he should employ
\n" ); document.write( "54
\n" ); document.write( "18
\n" ); document.write( "20
\n" ); document.write( "16
\n" ); document.write( "

Algebra.Com's Answer #751346 by htmentor(1343)\"\" \"About 
You can put this solution on YOUR website!
The job will take 36 people x 15 days = 540 people-days to complete
\n" ); document.write( "This means, for example, that it would take one person 540 days,
\n" ); document.write( "18 people 30 days, etc. to complete
\n" ); document.write( "Thus, to finish in 10 days, the total number of people required is 54
\n" ); document.write( "So he needs to hire 18 additional workers
\n" ); document.write( "