document.write( "Question 1134054: 36 people can construct a house in 15 days but the owner would like to finish the work in 10 days how many more workers he should employ
\n" ); document.write( "54
\n" ); document.write( "18
\n" ); document.write( "20
\n" ); document.write( "16
\n" ); document.write( "

Algebra.Com's Answer #751345 by ikleyn(52781)\"\" \"About 
You can put this solution on YOUR website!
.
\n" ); document.write( "The entire construction work is 36*15 = 540 working days.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "To complete it in 10 days, \"540%2F10\" = 54 workers are needed.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "So, additional 54 - 36 = 18 workers should be employed.\r
\n" ); document.write( "
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "
\n" ); document.write( "
\n" );