document.write( "Question 1134054: 36 people can construct a house in 15 days but the owner would like to finish the work in 10 days how many more workers he should employ
\n" );
document.write( "54
\n" );
document.write( "18
\n" );
document.write( "20
\n" );
document.write( "16 \n" );
document.write( "
Algebra.Com's Answer #751345 by ikleyn(52781)![]() ![]() You can put this solution on YOUR website! . \n" ); document.write( "The entire construction work is 36*15 = 540 working days.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "To complete it in 10 days, \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "So, additional 54 - 36 = 18 workers should be employed.\r \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |