document.write( "Question 1131997: Hi\r
\n" ); document.write( "\n" ); document.write( "it takes 15 days for 10 workers working 8 hours a day to finish an order. How many workers working 4 hours a day would be needed to finish the order in 10 days.\r
\n" ); document.write( "\n" ); document.write( "thanks
\n" ); document.write( "

Algebra.Com's Answer #748773 by joshuajz(12)\"\" \"About 
You can put this solution on YOUR website!
15 people w/ 80 hours of work being done a day. That's a total 1200 hours to complete the project. 1200/10 = 120 hours needed a day. 120/4 = 30 workers.\r
\n" ); document.write( "\n" ); document.write( "Therefore 30 workers are needed.
\n" ); document.write( "