document.write( "Question 1126669: It took 6 people to paint several offices in 5 days. How many more people need to be hired to complete the same job in 3 days? \n" ); document.write( "
Algebra.Com's Answer #743007 by ikleyn(52788)![]() ![]() You can put this solution on YOUR website! . \n" ); document.write( "This job requires 6*5 = 30 worker-days.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "To complete it in 3 days, you need \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Hence, 4 workers need to be added to the given 6 workers.\r \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |