document.write( "Question 1126669: It took 6 people to paint several offices in 5 days. How many more people need to be hired to complete the same job in 3 days? \n" ); document.write( "
Algebra.Com's Answer #743007 by ikleyn(52788)\"\" \"About 
You can put this solution on YOUR website!
.
\n" ); document.write( "This job requires  6*5 = 30 worker-days.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "To complete it in  3  days,  you need   \"30%2F3\" = 10 workers.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Hence,  4  workers need to be added to the given  6  workers.\r