document.write( "Question 1122714: Vivek,ramesh,bhuvan divide a work amongst themselves in the ratio 2:3:5.Their rates of work are in the ratio 1:2:3.It takes vivek 12 days to complete his part.What is the amount of work completed by them in 8 days from the start? \n" ); document.write( "
Algebra.Com's Answer #738875 by Boreal(15235)\"\" \"About 
You can put this solution on YOUR website!
If it takes V 12 days to do 2 pieces of work, in one day he does 2/12 and in 8 days 16/12 or 4/3.
\n" ); document.write( "R does it twice as fast or 1/3 in one day and 8/3 in 8 days.
\n" ); document.write( "B does it 3 times as fast as V or 1/2 per day or 4 pieces in 8 days.\r
\n" ); document.write( "\n" ); document.write( "After 8 days, they have completed 4/3 +8/3 + 4=8 pieces of work