document.write( "Question 1107638: Using new equipment, a worker finished 4 more parts in an hour than was planned and fulfilled his daily task not in 8 hours, but in 6 hours. How many parts did the worker have to finish during the day according to the schedule? \n" ); document.write( "
Algebra.Com's Answer #722661 by ikleyn(52943) You can put this solution on YOUR website! . \n" ); document.write( "Using new equipment, a worker finished 4 more parts in an hour than was planned and fulfilled his daily task not in 8 hours, \n" ); document.write( "but in 6 hours. How many parts did the worker have to finish during the day according to the schedule? \n" ); document.write( "~~~~~~~~~~~~~~~~~~~\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \r\n" ); document.write( "Let the old rate is \"r\" parts per hour (now unknown value).\r\n" ); document.write( "\r\n" ); document.write( "\r\n" ); document.write( "The condition says: Now he produces 4 more parts in one hour than before in 6 hours:\r\n" ); document.write( "\r\n" ); document.write( " In other words, the new rate R = 6r+4 parts per hour.\r\n" ); document.write( "\r\n" ); document.write( "\r\n" ); document.write( "Working at this rate, he will produce 8*R = 8*(6r+4) = 48r + 32 parts in 8-hour working day.\r\n" ); document.write( "\r\n" ); document.write( "\r\n" ); document.write( "That is all that we can say: nothing more and nothing less.\r\n" ); document.write( "\r\n" ); document.write( "\r\n" ); document.write( "At given condition IT IS NOT POSSIBLE to get a concrete value as a single answer.\r\n" ); document.write( "\r \n" ); document.write( "\n" ); document.write( "------------------------- \n" ); document.write( "So, I'd say: this description is as clear as it is at the dark night with no light.\r \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |