document.write( "Question 1102774: If the owner of a house can paint it entirely in 20 days but a professional can paint in 14 days, then how much time will it take to paint the entire house if both painters worked together?\r
\n" ); document.write( "\n" ); document.write( "Please provide me steps. I don't know if I answered this correctly.
\n" ); document.write( "

Algebra.Com's Answer #717501 by josgarithmetic(39631)\"\" \"About 
You can put this solution on YOUR website!
R, rate
\n" ); document.write( "T, time
\n" ); document.write( "J, job, amount of work, piece of work
\n" ); document.write( "RT=J, basic work rates rule\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "The work rates for the owner and the professional painter can take the rate unit of \"HOUSE%2FDAY\", and if they work together, the individual rates are simply ADDED.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "You really do not need to use the RT=J work rate rule.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Owner works at \"1%2F20\" house per days.
\n" ); document.write( "Professional works at \"1%2F14\" house per days.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Combined, \"1%2F20%2B1%2F14=%281%2F20%29%287%2F7%29%2B%281%2F14%29%2810%2F10%29\"\r
\n" ); document.write( "\n" ); document.write( "\"7%2F140%2B10%2F140\"\r
\n" ); document.write( "\n" ); document.write( "\"17%2F140\", in \"HOUSES%2FDAY\"; \r
\n" ); document.write( "\n" ); document.write( "You want the reciprocal for how many DAYS for 1 house.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"140%2F17\" \"DAYS%2FHOUSE\"\r
\n" ); document.write( "\n" ); document.write( "\"highlight%288%264%2F17%29\"\"days\"\r
\n" ); document.write( "\n" ); document.write( "About 8 and a quarter days.
\n" ); document.write( "