document.write( "Question 1086672: 4 men planned to complete a piece of work in 10 days,3 men worked for 4 days after which 4 men were employed.find the total number of days taken to complete the work? \n" ); document.write( "
Algebra.Com's Answer #700894 by MathTherapy(10552)\"\" \"About 
You can put this solution on YOUR website!
4 men planned to complete a piece of work in 10 days,3 men worked for 4 days after which 4 men were employed.find the total number of days taken to complete the work?
\n" ); document.write( "
It depends!
\n" ); document.write( "In 4 days, 3 men completed: \"3%2F10\" of the job, leaving \"7%2F10\" undone.
\n" ); document.write( "Now, to complete the remaining \"7%2F10\" of the job, how many men are working? Is it:
\n" ); document.write( "1) the original 4, plus the newly-employed 4, for a total of 8?
\n" ); document.write( "2) the 3 that worked for 4 days, plus the 4 newly-employed 4, for a total of 7?
\n" ); document.write( "3) the 4 newly-employed for a total of 4? \n" ); document.write( "