document.write( "Question 1071843: Four hundred men could do the job in 10 days. Paul had 600 men on the job for 5 days. How many men did he need for the next 5 days to finish the job on time? \n" ); document.write( "
Algebra.Com's Answer #686752 by addingup(3677)\"\" \"About 
You can put this solution on YOUR website!
400 in 10 days = 1 man in 4,000 days
\n" ); document.write( "600 in 5 days = 1 man in 3,000 - need 1,000 more days and 1,000/5 = 200 men
\n" ); document.write( "