document.write( "Question 1068638: It takes 24 days for 8 workers to complete painting a building, how many days will it take 18 workers \n" ); document.write( "
Algebra.Com's Answer #683882 by josgarithmetic(39618)\"\" \"About 
You can put this solution on YOUR website!
\"8%2Ar%2A24=18%2Ar%2Ax\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"x=%288%2A24%29%2F18\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"x=%288%2A4%2A6%29%2F%286%2A3%29\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"x=32%2F3\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"x=10%262%2F3\"\r
\n" ); document.write( "\n" ); document.write( "To the nearest whole day, 11 days.