document.write( "Question 1066910: It took two people to complete carpeting in 10 days. How many more carpenters need to be hired to complete the same job in 4 days? \n" ); document.write( "
Algebra.Com's Answer #682142 by ikleyn(52777)\"\" \"About 
You can put this solution on YOUR website!
.
\n" ); document.write( "It took two people to complete carpeting in 10 days. How many more carpenters need to be hired to complete the same job in 4 days?
\n" ); document.write( "~~~~~~~~~~~~~~~~~~~~~~~~~~~~\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "
\r\n" );
document.write( "1.  \"It took two people to complete carpeting in 10 days\"  --->  it means that the entire job is 2*10 = 20 man-days.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "2.  To complete it in 4 days, \"20%2F4\" = 5 workers are needed.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "3.  Since you just have two workers ready, you need 5-2 = 3 additional carpenters.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "Answer.  3 additional carpenters are needed.\r\n" );