document.write( "Question 1064709: 15 men can do a work in 210 days.if 15 additional men engaged every after 10 days, in how many days the work be finished? \n" ); document.write( "
Algebra.Com's Answer #679807 by ankor@dixie-net.com(22740)![]() ![]() You can put this solution on YOUR website! 15 men can do a work in 210 days. \n" ); document.write( "Find how many man-days required to complete the job \n" ); document.write( "15 * 210 = 3150 man days \n" ); document.write( ": \n" ); document.write( "if 15 additional men engaged every after 10 days, in how many days the work be finished? \n" ); document.write( ": \n" ); document.write( "Days - manhr - Tot manhr \n" ); document.write( " 10 - 15*10=150 - 150 \n" ); document.write( " 20 - 30*10=300 - 450 \n" ); document.write( " 30 - 45*10=450 - 900 \n" ); document.write( " 40 - 60*10=600 - 1500 \n" ); document.write( " 50 - 75*10=750 - 2250 \n" ); document.write( " 60 - 90*10=900 - 3150 man-hrs complete the job \n" ); document.write( ": \n" ); document.write( "It will take 60 days and a total of 90 men will be working then \n" ); document.write( " \n" ); document.write( " |