document.write( "Question 1053831: 40 men can complete a piece of work in 40 days.They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in how many days ? \n" ); document.write( "
Algebra.Com's Answer #669013 by josgarithmetic(39618)![]() ![]() ![]() You can put this solution on YOUR website! RT=J relates constant work rate, time, and quantity of jobs. Your example refers mostly to 1 job. If r is one-man work rate and there are n men working on the same job, the rate of this group is \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Look at how much of the job is done every 10 days...\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Basic plan for work was \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Now check each ten-day increment of work done. \n" ); document.write( "- \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "- \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "- \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "- \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "- \n" ); document.write( "What is the sum up to these end of 40 days? \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "Keep going... \n" ); document.write( "- \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "- \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "- \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "- \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "- \n" ); document.write( "What is the total sum of the job up to these 80 days? \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "THIS IS ALL OF THE 80 DAYS. \n" ); document.write( " |