document.write( "Question 1036966: If it takes a crew 9 days to do 80% of the job, how many more days will it take to finish the job 100% \n" ); document.write( "
Algebra.Com's Answer #651652 by josmiceli(19441)\"\" \"About 
You can put this solution on YOUR website!
Their rate of working is:
\n" ); document.write( "\"+.8+%2F+9+\" jobs / days
\n" ); document.write( "Divide top and bottom by \"+.8+\"
\n" ); document.write( "\"+1+%2F+11.25+\" jobs / days
\n" ); document.write( "\"+11.25+-+9+=+2.25+\"
\n" ); document.write( "The job can be finished in 2.25 days