Algebra.Com's Answer #648548 by josmiceli(19441)\"\" \"About 
You can put this solution on YOUR website!
3 workers can finish painting a house in 2 days
\n" ); document.write( "1/3 that number of workers will take 3 times as long, so
\n" ); document.write( "1 worker can finish painting a house in 6 days
\n" ); document.write( "-------------------------------------
\n" ); document.write( "6 workers will take 1/6 as long to paint a house, so
\n" ); document.write( "6 workers can finish painting a house in 1 day
\n" ); document.write( "---------------------------------------
\n" ); document.write( "5 houses will take 5 times as long, so
\n" ); document.write( "6 workers can finish painting 5 houses in 5 days