document.write( "Question 1029875: A team of 12 painters can paint a bridge in 20 days. How long would it take 1 painter? How long would it take 16 painters? If the job is to be completed in 15 days, how many painters would be required? \n" ); document.write( "
Algebra.Com's Answer #644812 by ikleyn(52908)\"\" \"About 
You can put this solution on YOUR website!
.
\n" ); document.write( "
\r\n" );
document.write( "A team of 12 painters can paint a bridge in 20 days. \r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "How long would it take 1 painter?   - Answer. 12 times 20 days, or 240 days.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "How long would it take 16 painters? - Answer. \"240%2F16\" = 15 days.\r\n" );
document.write( "\r\n" );
document.write( "\r\n" );
document.write( "If the job is to be completed in 15 days, how many painters would be required?  - Answer. \"240%2F15\" = 16 painters.\r\n" );