document.write( "Question 1028207: Six workers can paint 4 houses in 8 days. ahow many additional workers are neededi if the job of painting 8 houses must be finish in 4 days? \n" ); document.write( "
Algebra.Com's Answer #643402 by ankor@dixie-net.com(22740)\"\" \"About 
You can put this solution on YOUR website!
Six workers can paint 4 houses in 8 days.
\n" ); document.write( "how many additional workers are needed if the job of painting 8 houses must be finish in 4 days?
\n" ); document.write( ":
\n" ); document.write( "Find how many man-days required for each house
\n" ); document.write( "\"%286%2A8%29%2F4\" = 12 man-days per house
\n" ); document.write( "then
\n" ); document.write( "12 * 8 = 96 man-days to paint 8 houses
\n" ); document.write( ":
\n" ); document.write( "let w = no. additional workers required
\n" ); document.write( "4(w+6) = 96
\n" ); document.write( "4w + 24 = 96
\n" ); document.write( "4w = 96 - 24
\n" ); document.write( "4w = 72
\n" ); document.write( "w = 72/4
\n" ); document.write( "w = 18 additional men required
\n" ); document.write( "
\n" ); document.write( "
\n" );