document.write( "Question 1027978: At a local gravel yard, a large skip loader can move a large pile of gravel in 15 minutes. A smaller skip loader can move the same pile of gravel in 2.25 hours. How many minutes would it take the two skip loaders working together to move the gravel pile? \r
\n" );
document.write( "\n" );
document.write( "(Include units with your numerical answer. Round your answer to one decimal place.)\r
\n" );
document.write( "\n" );
document.write( "It would take about_______for the two skip loaders working together to move the gravel pile. \n" );
document.write( "
Algebra.Com's Answer #643246 by josgarithmetic(39620)![]() ![]() ![]() You can put this solution on YOUR website! Rate unit should be PILES per HOUR or as PILE per HOURS.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \r\n" ); document.write( "Which Skip Loader RATE, PILES per HOURS\r\n" ); document.write( "\r\n" ); document.write( "Large loader, 1/(1/4)=4\r\n" ); document.write( "\r\n" ); document.write( "\r\n" ); document.write( "Small loader, 1/(2&1/4)=1/(9/4)=4/9\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Combined rate for both loaders working together is \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "but if you want TIME for loading or moving 1 whole pile, then \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " |